Pavilion Buildings, Brighton scaffolding project in Brighton

    Pavilion Buildings, Brighton

    BrightonTwo phase perimeter and courtyard scaffold for parapet and guttering works

    Project Details

    C.N.M Scaffolding completed a two phase scaffold at Pavilion Buildings in Brighton, giving access for parapet and guttering works to every elevation of the block.

    Phase one was a full perimeter scaffold. Parapets and rainwater goods run the whole way round a building, so there is no useful partial answer. The structure went up around the outside, over trading shop fronts, on the Castle Square corner with the Royal Pavilion directly opposite.

    Phase two went round the back, and it is the more interesting half. The rear rainwater goods sit above a courtyard, so there was no ground to build off. The scaffold was built out over that courtyard from shear plates fixed to the wall, taking its load through the building rather than through the yard below it.

    From those plates it rose three lifts to a working platform set within a metre of the underside of the gutters, which is the height a roofer actually wants to work at rather than reaching up from a lift set too low. Access came in from the footpath, and the walkway was bridged across a lead roof so that nothing bore on the lead.

    Phase two was built to a scaffold design.

    This project utilised our commercial scaffolding, design & calculations and safe access scaffolding services, delivered to our full range of industry accreditations and safety standards. The project was located in Brighton, one of our key service areas across the south coast.

    Project Challenges

    Pedestrians were the problem in phase one, and they were a serious one. Castle Square is one of the busiest pedestrian spots in central Brighton, the shops below the scaffold were trading, and the Royal Pavilion is across the road. Erecting a perimeter scaffold means tubes and boards moving at head height over a pavement that does not empty.

    Banksmen were positioned at ground level for the duration of the erection to watch movement and hold people back from the working area, with signage and protective barriers marking it out. On a site this busy that is not a formality, it is the only thing standing between a lift of tube and the public, and it was genuinely hard to manage.

    Phase two swapped a crowd problem for a structural one. A courtyard gives you no ground to stand a scaffold on, so the structure had to be hung off the building instead, on shear plates fixed into the wall. That turns a routine access scaffold into a designed one, because the load now goes into the wall and somebody has to calculate whether it will take it.

    The lead roof added the last constraint. Lead is soft and it is a weathering layer, so a scaffold standing on it risks damaging the very surface keeping water out. The walkway was bridged across instead, spanning the lead rather than touching it.

    Health & Safety

    Banksmen were positioned at ground level throughout the phase one erection, monitoring pedestrian movement past a working scaffold on one of the busiest streets in the city.

    Signage and protective barriers marked out the working area, separating the public from the operation rather than relying on people to keep clear.

    Standards at pavement level were sleeved in yellow guarding, visible against the shop fronts to anyone passing close to them.

    The courtyard scaffold in phase two was built to a scaffold design, from shear plates fixed to the wall, with the walkway bridged across the lead roof so no load was taken on the lead.

    The scaffold was inspected at the statutory intervals for the duration of the hire. All operatives are CISRS certified.

    Key Highlights

    Full perimeter scaffold to every elevation
    Rear scaffold hung from shear plates over a courtyard
    Three lifts to a platform within a metre of the gutters
    Walkway bridged across a lead roof, nothing bearing on the lead
    Banksmen, signage and barriers for pedestrian management
    Phase two built to a scaffold design

    Conclusion

    Parapets and rainwater goods were reachable on every elevation of the block, including the rear ones standing above a courtyard with no ground beneath them.

    The shops below kept trading and the pavements stayed open, on a corner opposite the Royal Pavilion that never gets quiet.

    Project Gallery

    Phase one, the Castle Square corner with the Royal Pavilion opposite
    Phase one, the perimeter scaffold over the trading shop fronts
    Phase one, the Castle Square corner from across the road, with the Royal Pavilion beyond
    Phase two, the rear of the block from Palace Place
    Phase two, the rear elevation and chimney stack
    Phase two, looking back along Palace Place towards the Royal Pavilion